Case Study - NorthStar project
The opportunity
Most of the software process engineering tools today are proprietary and expensive, affordable only by large corporations.
The following table shows sales figures for the proprietary project management tools business. Even without considering free and pirated software usage, sales more than double over a five year period from 2001.
Year Sales in millions USD 2001 2502002 3502003 4202004 3902005 520
The growth of project management during the past decade has contributed markedly to project success rates. When 31% of the projects failed in 1994 , only 15% failed in 2002. Total cost of financial waste and budget overruns from challenged and failed projects is down. When $140 billion was wasted out of $250 billion spent in 1994 , only $55 billion out of $255 billion was wasted in 2002.Chaos Chronicles, Standish Group, 2002.
For the mid-sized organizations involved in project management, buying and maintaining the standard proprietary tools available is very expensive and there is no full fledged software engineering tool available in the open source space. . Whatever is available is confined to just scheduling, leaving out the other activities like estimation, WBS, dependency management, risk management, reviews, quality management, requirements management, design, testing wide open.
‘NorthStar’ the project management and software engineering tool, fills up this gap, and provides the users with the state of the art project management and software engineering tool , covering all facets of project management.
The Vision Provide the global software engineering community an open tool, which supports end to end software engineering project management which is easy to customize and affordable..
Scope of work - Develop a requirements capture module
Develop a work break down structure generation / capture module, which can be traced back to
requirements
Against the work breakdown structure capture planned completion date, revised completion date, actual completion date, planned effort, revised effort, actual effort, primary owner, dependent task (one only)
Compute earned value depending on 50-50 rule, that is when the task starts give 50% weightage and when the task ends give the balance 50% weightage
Compute and display critical path
Compute and display loading chart
Generate variance metrics for effort , schedule
Integrate with Bugzilla for defect details and generate one metrics on effort in testing Vs number of defects
Develop a risk management module which can capture risks, provide rating against each risk item based on the probability of occurrence and impact along with risk mitigation plan and status. Provide a facility to see the risks for a module , a project and for all my projects
The project execution strategy
There will be a core team defining the roadmap for the project and at any point in time, the roadmap for the next 1 year will be defined
The roadmap is broken down into schedules of 3 months each, and at any point in time, the schedules for the next 3 months will be available (wave planning/scheduling)
The project will have a project manager
The project will follow water fall model, and the duration of every waterfall cycle will be 3 months at the end of which there will be releasable code with additional functionality available for release
The core functionality will be developed by a dedicated in house team and the not so core functionality will be offered to university students to develop, with support from the core team
The project will use as many reusable code as possible
The project team
Project manager - Allan
Architect - Sushil
Quality assurance - Kent
Development team - Madan, Rajesh, Abu, Krishnan, Renuka, Mary ( Stationed in India) , Tony - team lead;
Development team - Arnold, Marina , Dave, Silvester , Jerry, Paul , Jason , Jose (Stationed at USA) , Alice - team lead;
Unit and component testing is done at the respective locations.
System testing is done in India
Project Sponsor - Varun;
Product manager - Abhishek
Technology used
Java, turbine, PHP, Apache, SVG, Linux
Project estimates
The project size is 40 KLOC (Kilo lines of code or 40,000 lines of code) and will take 1000 person days
Historical information used: Data from previous similar projects shows that a programmer can write an average of 40 LOC/day for Java, which is the main platform for Northstar.
Assumptions
enough funding will be available
French, German and Japanese versions will be available along with English version
the system will work best on Mozilla Firebird and Internet Explorer
will work on Linux, Windows
will work only on web and will not work in a client-server mode
all the reports will be available at the press of a button (maximum processing time will be less than 5 seconds)
the system will meet its performance criteria on any network with bandwidth 128 kbps and above
Flexibility matrix for the project
Schedule - least flexible
Scope - moderately flexible
Cost - most flexible
The domain NorthStar is built around the PMBOK* (project management body of knowledge by PMI* , project management institute) and comprises of the following knowledge areas and it is important for the project teams working on this project have the basic understanding of the project management body of knowledge. request you to go through the details given below, to get a broad picture of the project management body of knowledge.
Project Integration Management
Describes the processes required to ensure that the various elements of the project are properly coordinated.
It consists of:
Project Plan Development
Project Plan Execution
Integrated Change Control
The key concepts to be understood to practice project integration management are;
Role of a project manager as integrator,
Project plan development,
Contents of a project plan,
Project plan execution,
Integrated change control - change management systems / processes,
Importance of historical information / pitfalls in collecting data,
Corrective actions / preventive actions,
Project plan updates and revisions,
Project plan approval,
Project plan baselines,
Change control board - CCB,
Kick off meeting,
Work authorization system,
Change requests,
Configuration management,
Project management information system,
Earned value management system - Variations of earned value calculation,
Project planning methodology
Project Scope Management
Describes the processes required to ensure that the project includes all the work required and only the work required, to complete the project successfully. Comprises of:
Initiation,
Scope Planning,
Scope Definition,
Scope Verification,
Scope Change Control,
The key concepts to be understood to practice project scope management are:
Work breakdown structure,
Project initiation,
Project charter,
Scope definition and decomposition - characteristics of a good scope definition,
Scope verification,
Scope management plan,
Project selection methods and criteria,
Constraints,
Structure of a scope statement,
Scope management,
WBS dictionary,
Management by objectives - MBO,
Management by wandering around - MBWA.
Project Time Management
Describes the processes required to ensure timely completion of the project. It consists of:
Activity Definition
Activity Sequencing
Activity Duration Estimating
Schedule Development
Schedule Control
The key concepts to be understood to practice project time management are:
Scheduling
Crashing
Fast tracking
Estimation / re estimation
Network diagrams
Dependencies mandatory / discretionary / external
Logic diagrams and networks
The critical path
Slack / float / free slack / total slack / project slack
Calendar scheduling and time based networks
Management schedule reserve
PDM (precedence diagramming method) networks
PERT (program evaluation and review technique)
CPM (critical path method)
Scheduling with resource constraints
GERT (graphical evaluation and review technique)
Montecarlo simulation
BAR / GANTT charts
Milestone charts
Schedule management plan
Resource leveling
Lag
Flow charts
Heuristics
Variance analysis
Project Cost Management
Describes the processes required to ensure that the project is completed within the approved budget. Consists of:
Resource Planning
Cost Estimating
Cost Budgeting
Cost Control
The key concepts to be understood to practice project cost management are:
Cost estimating
Cost escalation
Cost estimation and the systems development cycle
Cost estimating process
Elements of budgets and estimates
Project cost accounting and management information systems
Budgeting using cost accounts
Cost summaries
Cost analysis with early and late start times
Effect of late start time on project net worth
Material expenditures and cash flow
Earned value analysis
Order of magnitude / budget / definitive
Project selection methods
BCR / NPV / IRR
Variable and fixed cost
Direct and indirect cost
Payback period
Opportunity cost
Present value
Sunk costs
Law of diminishing returns
Working capital
Straight line / accelerated
Life cycle costs
Value analysis
Project Quality Management
Describes the processes required to ensure that the project will satisfy the needs for which it was undertaken. It consists of:
Quality Planning
Quality Assurance
Quality Control
The key concepts to be understood to practice project quality management are:
Problem definition
Applying fix
Root cause analysis
Fish bone diagram / Ishikawa diagram
Pareto analysis
Quality planning
Quality assurance and quality control, cost of quality
Control chart
Definition of quality
Gold plating
Integrated quality management plan
Quality goals
Defect tracking systems
Metrics
Total quality management
Quality control tools
Quality audits
Continuous improvement
Marginal analysis
Responsibility for quality
Price of conformance and non conformance
Mean, median, mode, standard deviation
Six sigma
Variable, attribute
Probability
ISO 9000
CMMI
Malcolm Baldridge
Benchmarking
Just in time
Design of experiments
Sampling
Quality Gurus
Project Human Resource Management
Describes the processes required to make most effective use of the people involved with the project. It consists of:
Organizational Planning
Staff Acquisition
Team Development
The key concepts to be understood to practice project human resource management are:
PMCDF - project management competency definition framework
Role of project stakeholders
Servant leadership
Q12 practices
Project team structures
Career planning
Maslow's hierarchy
McGregor's X and Y
Herzberg
Responsibility chart
Team building
Powers of the project manager
Responsibilities of the project manager (human resource)
Enniagram types
Perquisites
Fringe benefits
Expectancy theory
Halo effect
War room
Recruitment
Cultural differences
Distributed teams
Virtual teams
Self directed teams
360 degree appraisals
Project Communications Management
Describes the processes required to ensure timely and appropriate generation, collection, dissemination, storage and ultimate disposition of project information. It consists of:
Communications Planning
Information Distribution
Performance Reporting
Administrative Closure
The key concepts to be understood to practice effective project communications management are;
Team size and communication channels
Types of communication
Communications planning
Formal and informal communication
Components of effective communication
Communication obstacles
Structure of a communication plan
Communications management plan
Effective meetings
Active listening
Body language
Administrative closure
Knowledge management
Communication control
Communication in virtual teams
6 thinking hats
Project Risk Management
Describes the processes concerned with identifying, analyzing, and responding to project risks. It consists of:
Risk Management Planning
Risk Identification
Qualitative Risk Analysis
Quantitative Risk Analysis
Risk Response Planning
Risk Monitoring and Control
The key concepts to be understood to practice project risk management are:
Risk identification
Sources of risk
Risk identification techniques
Risk checklist
Application of cause and effect diagram in risk analysis
Risk likelihood
Risk impact
Risk priority
Risk transference
Risk avoidance
Risk reduction
Contingency planning
Risk acceptance
Risk management principles
Risk management caveats
Expected value
Decision trees
Uncertainty and pay off tables
Simulation
Risk rating matrix
Risk management plan
Project Procurement Management
Describes the processes required to acquire goods and services from outside the performing organization. It consists of:
Procurement Planning
Solicitation Planning
Solicitation
Source Selection
Contract Administration
Contract Closeout
The key concepts to be understood to practice project procurement management are:
Forms of contracts
Purchase order
Negotiation
Incentives
Procurement management process
Legal terms
Types of contracts and their merits and demerits from the buyer's perspective
Essentials of a contract
Procurement documents
Non competitive procurement
Make or buy
Just in time
80/20
ABC analysis
Formal acceptance
Bidder's conferences
Financial closure
Contract performance reporting
Procurement audit
Product verification
Evaluation criteria
Procurement management plan
Special provisions
Contract template
Proclivity
Qualified seller lists
Advertising
Centralized and decentralized contracting
Procurement management
Contract interpretation
Letter of intent
Update and archive records
Lessons learned
Contract file