Transportation Planning Casebook/Sydney F6 Motorway
Reference material by Wikibooks contributors. This retains its source identity and is not 411 news reporting.
Sydney’s population increase over the past decade has been a major contributor to traffic delays in the southbound and northbound roads. In the recent years, WestConnex’s expansion of the M4 and M5 helped ease the congestions of motor vehicles in residential/ commercial areas. The F6 Extension Stage 1 is another Sydney project which is currently under the initial planning phase. South Sydney experiences daily road congestion and unreliable travel time, especially between Kogarah and Sydney CBD on the Princess Highway.
Stage 1 of the F6 motorway is a 4 km link road which will connect President Avenue, Kogarah to the new WestConnex M5 motorway at Arncliffe. This will provide quick connects to Sydney CBD, M4, Inner west and Parramatta as it lies parallel to Princess Highway and avoids 26 sets of traffic lights. By reducing the number of trucks on roads and improving travel time for all travellers, the F6 motorway aims to aid the residential areas of Kogarah by providing more quieter streets. In addition, local road users and busses will have easier accessibility to inner roads without having to wait in traffic. This will ultimately support the future growth of South Sydney by connecting it to the Greater Sydney region for increased productivity.
Additional benefits include:
Easy access bicycle and pedestrian pathways
Over 3250 jobs created during construction phase
Improved air-quality
Stage 1 of the F6 extension is currently at its environmental impact stage with construction beginning in 2020 and aiming to be complete by 2024. After stage 1 is complete the F6 extension aims to expand from Sydney CBD to Loftus, approximately 20 km. The total cost of this project is said to be around $3 billion AUD.
Key Features
Twin tunnels linking President Avenue at Kogarah to M5 motorway at Arncliffe.
Tunnels stubs constructed for future F6 extension
Minor upgrades to President avenue & Princess highway to accommodate for the increase in vehicle capacity.
Larger pedestrian and bicycle pathways between Bestic Street, Brighton – Le- Sands to Civic Avenue, Kogarah.
New bridge over President Avenue, Kogarah.
Additional power supply lines in the area.
List of Stakeholders
+
Tabulated List of Actors for F6 Motorway ExtensionInternal StakeholdersExternal Stakeholders NSW Government
Roads & Maritime Services NSW
Building Contractors (Not defined yet)
Project Managers (Not defined yet) Pedestrians
Motor vehicle drives / truck drivers
Local residents near construction zones
Local businesses
Timeline of Events
F6 Motorway Extension Stages https://www.buildsydney.com/f6-freeway-route-southconnex/
Stage 1 – Connects President Avenue in Kogarah to the M5 tunnels at Arncliffe
Stage 2 – Connects Taren Point to Stage 1 at Kogarah
Stage 3 – Connects Princess Highway at Loftus to Stage 2 at Taren Point
Stage 4 – Connect Princess Highway at Waterfall to Stage 3 at Loftus
+
Timeline of Events for the F6 Motorway ExtensionProject EventDate of EventDescriptionAnnouncement of project May 2017NSW Government announces the project will proceed with Stage 1 of the F6 Motorway Extension.https://www.rms.nsw.gov.au/documents/projects/sydney-south/f6/f6-project-overview-201811.pdfCommunity consultation – Part 1October 2017 - December 2017Preliminary project information shared with general public - early stage consultation regarding project scope with affected local residents commenced.EIS PreparationDecember 2017 NSW Government begins with preparing the EIS based on SEARS (Secretary’s Environmental Assessment Requirements).Community consultation – Part 2June–July 2018After additional project and design information was released, a second period of community consultation was opened.EIS placed on public exhibition December 2018486 community submission were received in response from community consultations regarding the EIS.https://majorprojects.accelo.com/public/537bcd0106384bb9c91a6d8aefcf180f/00.%20F6%20Extension%20Submitters%20List.pdfTendering opens 18 February 2019Pre-registration for contractor tendering begins.https://tenders.nsw.gov.au/rms/?event=public.rft.showArchived&RFTUUID=5822A4FA-D8FA-DCFC-7440E02876A871BCConstruction expected to commenceSeptember 2020 Scheduled major works expected to commence at both ends of the tunnel simultaneously. Expected completion of project December 2024The F6 Motorway project is scheduled to be completed and open for public use.https://majorprojects.accelo.com/public/d4da5d3b9654104ea8ff64170c4a1a43/01.%20F6%20Extension%20Stage%201%20EIS_Vol%201A_ToC_Executive%20Summary_Chapters%201%20to%207.pdf
Policy & Service Issues
During October and December, Roads and Maritime (RMS) ran community engagements and consultations to gather feedback on the concept design of the new F6 Extension Stage 1.https://www.rms.nsw.gov.au/documents/projects/sydney-south/f6/f6-extension-stage-1-community-feedback-report-2018-06.pdf
There was significant backlash from the South Sydney community in regards to air pollution and acquisition of local parkland, Rockdale Bicentennial Park to be specific.
In summary, the feedback focussed on seven key topics:
Community amenity, health and safety (19%);
Property and access (19%);
Local traffic (15%);
Air quality (14%);
Environmental impacts (13%);
Construction impacts (7%);
Public and active transport infrastructure (4%);
Other (9%).
The Environmental Impact Statement (EIS) extensively details the assessment and solutions to many of the issues brought to light by the community of Southern Sydney in significant detail. The main issues and responses can be summarised in the table below:
Community Concern RMS Responsehttps://v2.communityanalytics.com.au/rms/f6/mapCommunity amenity, health and safetySafety of all road users, in particular the impacts that the developments would have on pedestrian safety.The tunnel will not be accessible by pedestrians or bicycles.
RMS is investigating surface options for cyclists and pedestrian infrastructure to be incorporated into the design. Project impacts on local community gardens, greenspace and facilities.
Concerns in regards to losing local sporting fields (Rockdale Bicentennial Park, skate park)RMS has been working closely with Bayside and the local community on how best to restore the facilities. The amenities will be upgraded. During construction, the skate park will be relocated. Property and Access Concerns about land acquisitions F6 Extension Stage 1 has been designed to minimise impact to property; i.e. underground tunnels.
Using existing RMS owned landVibration and Noise Pollution Dilapidation surveys, any damage to be rectified at no cost to the landowner.
Noise and vibration limits, monitoring systems and mitigation measures will be put in place.
An acoustic shed will be installed to act as a noise barrier to construction noise. Local Traffic Concerns in regards to worsening local traffic conditions.
Additional heavy vehicle movements. Transport movements to be scheduled outside peak travel times whenever possible.
During operation, traffic will be reduced, bus travel times will be improved.
Link to and extension of existing shared cyclist and pedestrian path. Air Quality Location of unfiltered ventilation outlets in close proximity to schools, hospitals, play fields and parks, and young children and the elderly. A scientific review on the impact of the emissions from tunnel ventilation was undertaken. The findings indicated that the emissions would have negligible impacts on the local communities given the height at which the emissions would be released.
Monitoring of emissions will occur 24/7 in line with new EPA regulations for tunnel emissions. Environmental Habitats for native flora and fauna within Rockdale Bicentennial Park and local fish species.No presence of endangered native species.
Temporary loss of aquatic and riparian habitat to be reinstated with trees, wetlands and vegetated area to be replaced. ConstructionContaminated spoil removal, air pollution (dust) and increased heavy vehicle movements. Limiting construction hours, acoustic sheds to manage spoil ad noise.
Permanent operational infrastructure will be built as well as drainage and water management facilities. Road pavement and finishing works will occur at the end of the project.Public and Active Transport InfrastructureRequests for the provision of additional pedestrian crossing and/or bridges.RMS, with Bayside Council, are investigating surface options for cyclists and pedestrian infrastructure to be incorporated into the project design. OtherProject cost and tolling concerns.Project cost: $2.2-$2.6 billion.
Tolled road to provide a fair and equitable means to help fund the project. i.e. people using infrastructure will help pay for it and ongoing maintenance.General suggestions on alternative alignment and size of project. General comments in regards to future transport strategies as issued by Transport for NSW.
Environmental,Cost,Health ,Community Amenity and Safety Issues
1.Environmental issues
Traffic impacts
Source of Issues : loss of on street parking ,congestion on the road ,potential changes in traffic on surface roads including potential impacts of toll avoidance
Noise and vibration
Source of Issues : Demolition noise ,construction noise , Construction vibration ,operational noise and vibration, structural integrity of building
Social and economic impacts
Source of Issues : Local businesses , construction fatigue
Air quality
Source of Issues : Background concentration , all sources other than road traffic for example natural sources , industry and domestic activity.
Source of Issues :Surface of road ventilation outlet concentration ,the contribution of pollutants from the surface road network.
Source of Issues : Ventilation outlet concentration , the contribution of pollutants from tunnel ventilation outlets.
Source of Issues : Vehicle emissions and modify dust generating activities during windy weather condition.
Climate Change Risk and Greenhouse Gas
Source of Issues : Changes in the rainfall intensity and sea level rise due to the construction impact
2.Cost Issues
Source of Issues:the project is request for money cost up to $35 billion for the planning and development phases of the project.
Environmental impact and request for $2.2 to $2.6 billion Extension Stage one.
3.Health Issues
Source of Issues: People are suffocating from the impact of ventilation outlets ,People are impact from the dust during the construction.
4.Community Amenity and safety
Source of Issues: impacts on community access to local facilities and green space.
Discussion Exercises & Class Activities
Motorways have a time saving and cost trade off. What techniques can Transport for NSW use to promote usage of the motorway to reduce congestion?
How to improve the F6 Extension Motorway?