CACS/Glossary/ACWP

Reference material by Wikibooks contributors. This retains its source identity and is not 411 news reporting.

Actual Cost of Work Performed (ACWP) (Project Management) The total direct and indirect costs of accomplishing work completed to date. It usually refers either to a given time period or to a completed project phase, activity, or task. Some management techniques compare it to a budget to determine a variance or status. In other cases, when it is usually called earned value, ACWP may be used to determine interim payments to a contractor.