REQUIREMENTS ANALYSIS
Requirements analysis is the phase of the project where the requirements of a project are carefully defined. A requirement is a documented need or a description of what a system must accomplish. It is a statement that identifies a necessary attribute, capability, characteristic, or quality of the product of a project.
Product
The project's material outcome is its product. The product may be a service, event or a material object. It includes all necessary aspects of the deliverable including training, documentation, etc. Requirements focus on the product itself rather than the ways of achieving the product, leaving the implementation details for later. Requirements that focus on how the product is achieved are said to have implementation bias.
Requirements Statement
A requirements statement is a detailed accounting of project objectives. It describes the features, functions and performance constraints of the product. It provide the basis for accepting the product, or describes what must be accomplished for the product to be accepted.
The following are some useful techniques to understand user requirements:
Prototyping
Pilot
Use Case Modeling
describes relationship of a software product and its environment
JAD (Joint Application Design)
UML (Unified Modeling Language)
management tool for object oriented software design
Project Description Document
The Project Description Document and the Project Requirements are used to identify:
the high-level value of the project to the sponsor and users
gaps in the requirements when compared to the project scope
whether the list of requirements is complete and valid enough to move on to next phase
Project Requirements Document - OTN
all system inputs are defined
all system outputs are defined
requirements are validated with sponsors and users
business rules, special logic, and calculations are defined
gaps between the requirements and the scope are identified and filled
Requirement Characteristics
necessary range of inputs
carefully evaluated to be within the project scope
complete, accurate, and valid
Types Of Requirements
business
functional
technical
Traceability
track a requirement to documented need
Configuration Management
ensure descriptions of projects products are correct and complete
document physical and functional design characteristics
REFINE SCOPE
Scope statement will be included in the project plan
Scope of a project is usually defined during the initiation phase of a project but the scope can change as needed as more analysis is done
WBS (work breakdown structure)
WBS key concepts
hierarchical task list
decomposition of project into a collection of work units
use to determine the project work effort
basis for planning, schedule, budget
used to estimate resource requirements, activity durations, and costs
required to create a Gantt chart
will be included in the project plan statement
Phase = highest level element of the WBS
Work Package = lowest level element of the WBS
one person responsible for each item, although many may work on that item
formal approval should be obtained for each deliverable
authority to sign off should be clearly defined
depicted as
tree diagram (or hierarchy chart)
list in outline form with detailed items subordinated to higher-level items.
schedule and budget contained in WBS?
Activity or Task
may be of any size (a project is a very large activity or task)
sometimes the terms are synonymous
sometimes the terms are used to denote a piece of work at a particular level in WBS
e.g. a phase is broken into activities, and an activity into tasks
defined in each activity or task
duration
cost
resources
deliverables
SMART: activities or tasks should be
Specific
Measurable
Assignable
Realistic
Time-framed
Phase
highest level element of the WBS
grouping of activities in a project
meets a major milestone by providing a significant deliverable
e.g. requirements definition or product design document
a project is broken down into a set of phases for control purposes
phase is usually the highest level of breakdown of a project in the WBS.
Work Package
lowest level of the WBS at which project accounting is performed
usually a week or so in duration and performed by an individual or small work group
"Work Package" v "Task" v "Work Unit" v "Activity"
"task" or "work unit" or "activity" = all ambiguous
task could be high level, mid-level, or low level, i.e. summary task, sub-task
work package lowest level for which accounting is performed - unambiguous
best practices
keep work unit duration as short as possible
work teams should be small
hierarchy format e.g.
1.0 Main task 1
1.1 Subtask 1
1.2. Subtask 2
2.0 Main task 2
3.0 Main task 3
Deliverable
any item produced as the outcome of a project or any part of a project
project deliverable is differentiated from interim deliverables
interim deliverables result from activities within the project
deliverable must be tangible and verifiable
every element of the WBS (activity or task) must have one or more deliverables.
BUILD TEAM
Issues
Contract Labor
Outsourcing
Recruit The Best Candidates
ask mainly open questions
develop the interview questions
develop a mechanism to score responses
develop a comprehensive job specification
identify skills, knowledge, and attitudes required for the position
Attributes To Look For In A Candidate
a positive, team-player attitude
a goal oriented, Can do disposition
a knowledge of systems and user documentation
Resource Capabilities And Resource Availability
have the greatest impact on the actual duration of project tasks
have the greatest impact on the estimated per unit labor cost
RESPONSIBILITY ASSIGNMENT MATRIX
Maps Work To People
Authority Structure?
ESTIMATION TECHNIQUES
Top Down
estimate effort/cost/duration/risk of project or phase
looking at the project as a whole
comparing project to previously performed similar projects
methods of comparison
analogous estimating
direct comparison
parametric estimating
using an algorithm
experts
estimating from memory
ROM (Rough Order of Magnitude)
estimate effort/cost/duration/risk of project or phase
done early in a projects to get a ball park figure
about the same as top down.
Parametric
estimate effort/cost/duration or project or phase
using an algorithm
parameters that represent attributes of the project used to calculate
used in top-down estimating.
Analogous
estimate effort/cost/duration/risk of project or phase
estimating using similar projects or activities as a basis for determining
used in top-down estimating
Bottom Up
estimate effort/cost/duration or project or phase
breaking down into activities, tasks and sub-tasks
estimating the effort, duration and cost of each task and sub-task
combine all component estimates to determine the full estimate
determining duration through a bottom-up approach requires
sequencing and resource leveling to be done as part of the scheduling process.
Cost and Time Estimating Issues
scope
task requirements
resource availability
resource expense
original estimations vs actuals
FTE = Full Time Equivalent
SCHEDULE
Process For Creating Schedule
estimate time and resources for each work unit
historical data
expert judgment
determine dependencies between work units
level the resources
create checklists for each work unit
understand dependency relations between work units
FF, SS, FS, SF
Five Lists Required To Generate Schedule
deliverables
project tasks
required skills
available skills
time and resources per task
Items Needed To Justify The Schedule
the project critical path
actions you have taken
the tasks with time requirements
Sequencing Tasks
part of the scheduling process
tasks are positioned serially or parallel based on dependencies between them
sequencing results in a task network.
Dependencies: Types Of
mandatory
inherent in the nature of the work
often involve physical limitations
hard logic
discretionary
defined by project management team
soft logic
external
relationship between project and non-project activities
Milestones
points in time when a deliverable or set of deliverables is available
denote a significant event such as the completion of a phase
SMART criteria = Specific, Measurable, Assignable, Realistic, Time-framed
on gantt chart represented by black diamonds
on tracking gantt chart, slipped milestones represented by white diamond
an event: no duration or effort
must be preceded by one or more tasks
even the beginning of a project is preceded by a set of tasks, may be implied
Critical Path
path(s) in a project network that has the longest duration
series of activities that determines the earliest completion of the project
may be more than one critical path
critical path(s) may change during the project.
Float Or Slack
amount of time available for a task to slip before it delays the project end date
It is the difference between the task's early and late start dates.
Lead
minimum lapse of time between start of activity and start of overlapping activity
Lag
waiting time between two tasks
Gantt Chart
bar chart that depicts a schedule of activities and milestones
activities are listed along the left side of the chart
time line is listed along the top or bottom of the chart
activities are shown as horizontal bars
length of activity bars are equivalent to the duration of the activity
may be annotated with dependency relationships and other schedule-related information.
Network Diagram
graphic tool for depicting the sequence and relationships between tasks
forms of network diagrams
PERT Diagram
Critical Path Diagram
Arrow Diagram
Precedence Diagram
Pert (Program Evaluation And Review Technique)
scheduling technique that makes use of
dependency analysis and critical path to determine the duration of a project
slack to determine priorities of tasks
task durations are computed as (Optimistic + 4x Most likely + Pessimistic estimates) / 6)
Schedule
project time-line
identifies dates (absolute or relative to a start date) that
project tasks will be started and completed
resources will be required
milestones will be reached.
Sequencing Tasks
tasks are positioned serially or parallel based on dependencies between them
sequencing results in a task network.
BUDGET
Process For Creating - Bottom Up
determine cost of resources for each work unit
determine when those resources will be required
should have written approval from the project sponsor
Uses For Top Down Budget
confirm the customer's expected cost
validate detailed (bottom-up) budget when it is created
Budget Baseline
need budget and schedule to develop
show when the budget for each work unit will be spent
basis for budgets cash flow
basis for PV (BCWS) and EV (BCWP) (new terms?)
Management Reserve
funding for price changes that occur over the project life cycle due to -inflation- ?
Cost Budgeting
allocate cost estimates over time
four inputs to cost budgeting
cost estimates
WBS
project schedule
risk management plan
one output from cost budgeting
cost baseline
time phased budget
Fully Loaded Amounts For Hr Include
compensation
benefits
overtime
etc
COMMUNICATIONS PLAN
Communication Policies
There should be no arguments in front of the customer
Consultants should not discuss other clients while on-site
Communications Plan Should Include Communication:
purpose
senders
recipients
frequency
type
method
description
Information Needs Of End-User Management
main systems functionality
user involvement requirements
main deliverables planned delivery times
QUALITY PLAN
Quality Plan
create operation definitions for performance, and reliability
Project Review Process
provides a quality assurance measure for project performance
provides an independent evaluation of project performance/documentation
Quality Testing (Types Of)
unit test
component level
integration test
functionally grouped components
system test
the entire system as one entity
user acceptance test
should prove that the system operates to the specified requirements.
verification
alpha testing
simulated environment and simulated data
validation
beta testing
live environment and real data
audit testing
certifies system is ready for operation
Quality Checkpoints
Quality Assurance (QA)
making sure standards and procedures are effective and complied with
in some organizations QA is used to refer to the quality control function
satisfy standards
promote continual improvements
Quality Control (QC)
making sure deliverables comply with acceptance criteria
includes testing and reviews.
RISK MANAGEMENT PLAN
Risk
likelihood of the occurrence of an event
generally, the event is a negative one like project failure
event may also be a positive event, like the early completion of a task
price for opportunity
Risk Categories
technology risk
schedule risk
program evaluation and review technique (PERT)
Monte Carlo
financial risk
Choices To Handle Risk
accept
avoid
mitigate
Qualitative Risk Analysis
assess likelihood and impact of identified risks
Identify Potential Risks
historical information
nature of product and project
information gathering
Risk Assessment
part of risk management
planners identify potential risks and describe them
risks usually identified in terms of
symptoms
causes
probability of occurrence
potential impact
Risk Response
action that can be taken to address the occurrence of a risk event
Contingency Plans are collections of risk responses
Risk Response Control
responding to risk event occurrences throughout the project life cycle
taking corrective action is an aspect of risk response control
Risk Response Development
part of risk management
planners identify and define actions to be taken in case a risk occurs
such risk may be positive or negative
Six Processes Within The Area Of Risk Management:
Risk Management Planning
Risk Identification
Qualitative Risk Analysis
Quantitative Risk Analysis
Risk Response Planning
Risk Monitoring and Control
PROJECT PLAN
Project Plan – Key Concepts
other documents, such as WBS and SOW are fed into the project plan
very detailed and contains all the information about the project
a living document in that its contents can change over the life of the project
needs to be base-lined and all changes tracked
closes out the planning phase
Project Plan - Methods For Generating Support For
requesting input from stakeholders during planning process
clearly illustrating how the project relates to the company's objectives
Project Plan - Included In Project Plan
project scope
project definition
project objectives
project scope analysis (inclusion and exclusions)
project deliverables
project assumptions
project success criteria
project requirements
methodology description
project approach
work breakdown structure (WBS)
project estimates
project risk assessments
project resources (skills set needed, etc)
Project Plan : PP-TOSTR-SEE-BIST (mnemonic)
(T) - Table of Contents
(O) - Overview
(S) - Sponsors
(T) - Team Members
(R)- Requirements
(S) - Scheduled Tasks (WBS)
(E) - Expected Resources
(E) - Environmental Issues
(B) - Business Requirements
(I) - Implementation Plans
(S) - Support Plans
(T) - Training Plans - Nine Knowledge Areas, each = report, except integration (dummies pmp)
Integration
Scope
Time
Cost
Quality
Human Resources
Communication
Procurement
Risk
mnemonic: Rapper Ice-T seeks the HR department to take a CPR class
Ice-T - IST - integration, scope, time
seeks HR - CQ HR - cost, quality, HR
CPR - communication, procurement, risk
Project Plan - Steps To Creating A Project Plan
assemble all project planning elements
create an outline or table of contents
review outline with key stakeholders
adjust the plan according stakeholder feedback
write the comprehensive project plan
obtain formal approval