The Abalone Alliance (1977–1985) was a nonviolent civil disobedience group formed to shut down the Pacific Gas and Electric Company's Diablo Canyon Power Plant (DCPP) near San Luis Obispo on the central California coast in the United States. They modeled their affinity group-based organizational structure after the Clamshell Alliance which was then protesting the Seabrook NPP nuclear power plant in coastal New Hampshire. The group of activists took the name "Abalone Alliance" referring to the tens of thousands of wild California Red Abalone that were killed in 1974 in Diablo Cove when the unit's plumbing had its first hot flush.
The Abalone Alliance staged blockades and occupations at the DCPP Diablo Canyon Power Plant site between 1977 and 1982. Nearly two thousand people were arrested during a two-week blockade in 1981, exceeding Seabrook as the largest number arrested at an anti-nuclear protest in the United States.Daniel Pope. Conservation Fallout (book review), H-Net Reviews, August 2007.
History
The Diablo Canyon controversy started in 1963 when PG&E Pacific Gas & Electric scrapped its attempt to build the Bodega Bay NPP nuclear power plant at Bodega Head, 71 miles north of San Francisco. The Bodega struggle started in 1958, but was opposed by a group led by a University of California professor and young Sierra Club activist named David Pessonen. This was the first anti-nuclear power campaign in the US United States. The main reason that the facility was not built was due its location less than 1,000 feet from the fault fracture in Earth’s crust; a source of earthquakes zone that struck San Francisco in 1906.
Rather than face public opposition at Diablo Canyon, PG&E Pacific Gas & Electric approached the Sierra Club's president and cut a deal with certain board members where Diablo would be chosen rather than the Nipomo Dunes area. The wife of the Sierra Club president, who worked out the deal, would then be elected to PG&E Pacific Gas & Electric's board of directors. As part of the plan, the decision was made when Sierra Club board member Martin Litton was out of the country, the only member who knew of Diablo's history and importance.January 2011 The board was flown down to see the site in Frank Sinatra's Learjet with Danny Kaye on board providing entertainment. Kaye would later become opposed to nuclear power.
The Sierra Club president forbade any chapter from opposing Diablo Canyon, so The San Luis Obispo Chapter formed the Shoreline Preservation Conference to oppose the construction on the grounds that the area had been proposed as a state park, was a sacred Chumash Indian site, had some of the largest oak trees on the West Coast, was located on the second-to-last coastal wilderness area in California, and could be sitting on the fault that lightly shook Santa Barbara, CA California, in a 1927 earthquake. The internal dispute over Diablo Canyon was a primary reason for the split-up of the Sierra Club, that led to the formation of Friends of the Earth by David Brower.January 2011
In 1965, the Shoreline Preservation Conference demanded that regulators investigate the danger of faults near the proposed site, but this demand was ignored. In 1972 however, a Los Angeles news reporter uncovered a report by Shell Oil Company geologists, completed prior construction, of the existence of the Hosgri Fault 2½ miles offshore from the facility. And as a result of this discovery, regulators forced PG&E Pacific Gas & Electric to redesign and reinforce the facility.
Protests
During the late 1970s, the Abalone Alliance organized protests in San Luis County and regularly picketed PG&E Pacific Gas & Electric offices across the state. The Alliance published a newspaper, It's About Times, which provided a forum for activist debate. Separate groups within the Abalone coalition "developed their own foci and protest styles".http://books.google.com.au/books?id=nVR_vLOPfioC&pg=PA207&lpg=PA207&dq=conservation+fallout+review&source=bl&ots=kQv9zMgV2R&sig=JWVFkUZLXFrPlxLdr6EAGbouAvo&hl=en&ei=0iGuTYS8GYrcvQO_1tWPDw&sa=X&oi=book_result&ct=result&resnum=1&ved=0CBQQ6AEwADgK#v=onepage&q=protests&f=falseJuly 2026 Conservation fallout: nuclear protest at Diablo Canyon John Wills 2006 91
On August 7, 1977, 1,500 people demonstrated at the gate of Diablo Canyon, resulting in 47 arrests. The next year, 5,000 people rallied and 487 were arrested. On September 10, 1981, the Abalone Alliance occupied the site, leading to 1,960 arrests. Nearly 30,000 people showed up in support. At the end of the ten-day action, a 25-year-old engineer discovered a mirror image reversal in the seismic blueprints. PG&E Pacific Gas & Electric was forced to spend $3 billion and three additional years of repairs before reopening.February 2007 Anti-War Activists Daniel Ellsberg and Tom Hayden as well stars like Jane Fonda and Robert Blake and performers such as Jackson Browne, Bonnie Raitt, Crosby, Stills, Nash & Young, Linda Ronstadt, Peter Yarrow, Holly Near, Bruce Springsteen and the E Street Band, James Taylor, Carly Simon, Chaka Khan, The Doobie Brothers, Jesse Colin Young, Gil Scott-Heron, Tom Petty, Poco, Wavy Gravy and othersexcessive detail We do not need whole lineup, guys. July 2026 joined the anti-nuclear protests and movement. The mass jailings were described as a "tornado of talent." Jackson Browne defending his civil disobedience at a San Luis Obispo courthouse after his arrest for trespassing at the blockade (“I consider my actions to be patriotic”). In 1984, the Alliance organized the Peoples Emergency Response Plan, where affinity groups blockaded at the Diablo Gates over a four-month period.
In late 1981, Alliance activists primarily from Davis, CA California, and Sonoma, along with local opposition held an eight-day sit-in at the State Capitol, encouraging then-Governor Jerry Brown to use emergency powers to shut down the Rancho Seco Nuclear Generating Station. The plant was closed by a public vote in 1989, a decade before its operating license was to expire. Other Alliance activists went on to form the Livermore Action Group, the Vandenberg Action Coalition, and the Lenten Desert Experience at the Nevada Test Site. At its peak, there were over 60 groups who were affiliated with the Alliance, including Greenpeace and Alliance for Survival. The group was hit with one of the first known SLAPP strategic lawsuits against public participation suits in U.S. United States history, where the Pacific Legal Foundation and San Luis Obispo County attempted to legally obtain the names of all members and supporters, demanding that they pay for the costs of the 1981 blockade. The suit lasted nearly five years, before being withdrawn just before going before the U.S. United States Supreme Court.
The Mothers for Peace filed a legal challenge with the D.C. District of Columbia Circuit Court in an attempt to stop the operation of Diablo Canyon but was denied in November 1984. In January 1985, NRC Nuclear Regulatory Commission Commissioner Asselstine leaked a copy of the NRC Nuclear Regulatory Commission's secret transcripts to KRON‑TV television in San Francisco, documenting how the NRC Nuclear Regulatory Commission had illegally licensed Diablo Canyon without properly reviewing evacuation plans as previously required. The Mothers then reopened their challenge based on the leaked NRC Nuclear Regulatory Commission transcripts. Judge Robert Bork of the DC District of Columbia Court took the lead in denying the appeal April 25, 1986. Bork claimed that to look at the leaked transcripts would be judicial law ruled by courts of justice activism.January 2011
Diablo Canyon opens
The Diablo Canyon reactors were originally estimated to cost just over $300 million when PG&E Pacific Gas & Electric was first given permission to construct the facility. When finally opened in 1985, construction costs were $5.8 billion and financing costs nearly an additional $7 billion. After the 1981 blueprint mirror image mistake was discovered, the reactor's construction costs stood at $2.1 billion. PG&E Pacific Gas & Electric permission to go ahead with operation was reversed by the NRC Nuclear Regulatory Commission and the company was required to go through a major review and rebuild. PG&E Pacific Gas & Electric was unable to find further financing from any source to continue construction, until president Ronald Reagan ordered the United States Environmental Protection Agency to give the company nearly $2.5 billion in loans.January 2011
The controversy did not come to a close until December 1988 when the California Public Utilities Commission gave PG&E Pacific Gas & Electric a $54 billion 30-year, cost plus rate contract to operate DCPP Diablo Canyon Power Plant. It has been consideredJanuary 2011 the most controversial NPP nuclear power plant in U.S. United States history because of its location 2½ miles offshore from the Hosgri Fault.
References
Further reading
Brown, Jerry and Rinaldo Brutoco (1997). Profiles in Power: The Anti-nuclear Movement and the Dawn of the Solar Age, Twayne Publishers.
Lovins, Amory B. and Price, John H. (1975). Non-Nuclear Futures: The Case for an Ethical Energy Strategy, Ballinger Publishing Company, 1975, 0884106020
Natti, Susanna and Acker, Bonnie (1979). No Nukes: Everyone's Guide to Nuclear Power, South End Press.
Ondaatje, Elizabeth H. (c1988). Trends in Antinuclear Protests in the United States, 1984-1987, Rand Corporation.
Price, Jerome (1982). The Antinuclear Movement, Twayne Publishers.
Smith, Jennifer (Editor), (2002). The Antinuclear Movement, Cengage Gale.
Walker, J. Samuel (2004). Three Mile Island: A Nuclear Crisis in Historical Perspective, University of California Press.
Wellock, Thomas R. (1998). Critical Masses: Opposition to Nuclear Power in California, 1958-1978, The University of Wisconsin Press, 0299158500
Wills, John (2006). Conservation Fallout: Nuclear Protest at Diablo Canyon, University of Nevada Press.
External links
Abalone Alliance archivist site
Bodega Head controversy