Scientific Calculations with Julia Shortest Path Cost Minimization Traveling Salesman
In graph theory, the shortest path between two vertices (or nodes) of a graph is the path that connects the vertices and minimizes the sum of the costs associated with traversing each edge (or edge).
Suppose we want to travel from position 1 to position 6, minimizing the total distance to travel. First, we need to construct the adjacency matrix:
adjacency_matrix = [
0 2 4 0 0 0;
0 0 1 7 0 0;
0 0 0 0 3 0;
0 0 0 0 0 1;
0 0 0 2 0 5;
0 0 0 0 0 0
];
In practice, from position 1 to position 2 there are 2km, so the element (1,2) of the matrix has the value 2; from position 1 to position 3 there are 4km, so the element (1,3) of the matrix has the value 4; and so on, the adjacency matrix is constructed...
At this point, you need to install the Graphs, GraphPlot, and DataStructures libraries and construct the graph with the adjacency matrix:
using Graphs
G = SimpleDiGraph{Int16}(adjacency_matrix)
This results in a directed graph with 6 vertices and 8 arrows.
The graph's arrows are displayed:
path = collect(edges(G))
8-element Vector{Graphs.SimpleGraphs.SimpleEdge{Int16}}:
Edge 1 => 2
Edge 1 => 3
Edge 2 => 3
Edge 2 => 4
Edge 3 => 5
Edge 4 => 6
Edge 5 => 4
Edge 5 => 6
The costs of each arrow, i.e., the kilometers from one position to another, are established using Julia's "SortedDict" data structure:
using DataStructures
edgelabels = SortedDict(
(1,2)=>2,
(1,3)=>4,
(2,3)=>1,
(2,4)=>7,
(2,5)=>3,
(4,6)=>1,
(5,4)=>2,
(5,6)=>5
)
Display the graph:
using GraphPlot
nvertices = nv(G) # number of vertices
gplot(G, nodelabel=1:nvertices, edgelabel=values(edgelabels))
thumb|center|500px
Apply the Dijkstra algorithm to find the shortest path from vertex 1 to vertex 6:
path = enumerate_paths(dijkstra_shortest_paths(G,1),6)
4-element Vector{Int64}:
1
2
4
6
The shortest path is 1-->2-->4-->6 with a total cost of 10 km.