Introduction
Since the early 1900’s DC has utilized combined sewer overflow (CSO) systems to manage excessive rainwater. CSOs alleviate water from the sewer system, but can lead to sewage leaking into the drainage basins, the Potomac and Anacostia rivers, and Rock Creek. This system has deteriorated the river ecosystems, with Rock Creek being a recognized environmental hazard. Plans to revise the wastewater systems were first introduced in the late 1990s and early 2000s, aiming to improve the local environment and water quality.District of Columbia Water and Sewer Authority, Combined Sewer System Long Term Control Plan Final Report (2002-08-01), https://www.dcwater.com/sites/default/files/project/2023-09/documents/Long%20Term%20Control%20Plan.pdf, retrieved 2025-11-05
The DC Clean Rivers Project can be broken down into six subgroups: The Potomac River Tunnel, Anacostia River Tunnel, Piney Branch Tunnel, Sewer Separation, Green Infrastructure, and Combined Sewer Systems. One of the primary goals of the Clean Rivers Project is to construct tunnels and diversion systems below the existing sewer systems. These diversion systems use gravity to separate the flows and divert sewer wastewater to the existing Blue Plains Advanced Wastewater Treatment Plant.Clean Rivers Project DC Water https://www.dcwater.com/cleanrivers 2025-11-05 www.dcwater.com{
"type": "FeatureCollection",
"features": [
{
"type": "Feature",
"properties": {},
"geometry": {
"type": "Point",
"coordinates": [ -77.018739, 38.820178 ]
}
}
]
}Upon completion, the DC Clean Rivers Project will diminish CSOs in an average rainfall year by 96% across the entire District’s current system. The Anacostia River is predicted to have a 98% reduction in CSOs, 93% for the Potomac River, and 90% for Rock Creek. Additionally, the Project will reduce the likelihood of flooding in prone areas in the Northeast Boundary by an estimated 50% to 7% in any given year and reduce nitrogen leaked to the Chesapeake Bay by approximately 1 million pounds per year. The project also aims to implement more green infrastructure across 92 acres of impervious land at Rock Creek. In total, the project will encompass 18 miles of new tunnels, extending over 100 feet below ground. The Clean Rivers Project is the largest infrastructure project in the District’s history and is considered an ongoing success as the Anacostia River Tunnel was completed ahead of schedule.DC Water Board of Directors Extends Contract for CEO and General Manager David L. Gadis, Ensuring Continued Leadership and Progress DC Water https://www.dcwater.com/about-dc-water/media/news/dc-water-board-directors-extends-contract-ceo-and-general-manager-david-l#:~:text=Delivered%20major%20milestones%20in%20the%20Clean%20Rivers,sewer%20overflows%20and%20dramatically%20improve%20water%20quality 2025-11-05 www.dcwater.com
The Clean Rivers Project was conceptualized following the issuing of the Clean Water Act (CWA). The CWA regulates the discharge of pollutants and requires municipalities to develop Long-Term Control Plans (LTCPs) for CSOs.O'Cleireacain Carol May 2012 Cleaner Rivers for the National Capital Region: Sharing the Cost https://www.brookings.edu/wp-content/uploads/2016/06/0523-washington-dc-clean-water-ocleireacain.pdf Metropolitan Policy Program at Bookings The project was mandated by a 2005 consent decree between DC Water and the EPA that required the construction of a massive, multi-billion-dollar plan of deep underground tunnels and green infrastructure.$819 million contract awarded for DC Water’s final CSO tunnel https://www.asce.org/publications-and-news/civil-engineering-source/civil-engineering-magazine/article/2023/11/819-million-contract-awarded-for-dc-waters-final-cso-tunnel 2025-11-05 www.asce.org en-US By keeping the sewage from overflowing and discharging into natural water sources, the DC Clean Rivers Project aims to ensure compliance with the clean water quality standards set forth by federal law.
Timeline
+TimeEventJuly 2002District of Columbia Water and Sewer Authority publishes the Combined Sewer System Long Term Control Plan Final Report.2013CSO 019 Overflow Structure Project construction is completed and placed into permanent operation by March 2018.CSO 019 Overflow Structure Project DC Water https://www.dcwater.com/projects/cso-019-overflow-structure-project 2025-11-05 www.dcwater.com2013CSO 007 Diversion Sewer Project construction is completed and placed into permanent operation by March 2018.CSO 007 Diversion Sewer Project DC Water https://www.dcwater.com/projects/cso-007-diversion-sewer-project 2025-11-05 www.dcwater.comJanuary 2014Tingey Street Diversion Sewer Project construction is completed and placed permanent operation by March 2018.Tingey Street Diversion Sewer Project DC Water https://www.dcwater.com/projects/tingey-street-diversion-sewer-project 2025-11-05 www.dcwater.com2014M Street Diversion Sewer construction is completed and placed into permanent operation by March 2018.M Street Diversion Sewer Project DC Water https://www.dcwater.com/projects/m-street-diversion-sewer-project 2025-11-05 www.dcwater.com2014First Street Tunnel Project began construction.First Street Tunnel Project DC Water https://www.dcwater.com/projects/first-street-tunnel-project 2025-11-05 www.dcwater.comOctober 29,, 2015Mining begins on the Anacostia River Tunnel Project.Anacostia River Tunnel Project DC Water https://www.dcwater.com/projects/anacostia-river-tunnel-project 2025-11-05 www.dcwater.comOctober 2016First Street Tunnel Project is completed and begins operation.November 2016Anacostia River Tunnel Project is completed and begins operation.2019Design work begins on the Potomac River Tunnel.Potomac River Tunnel Project DC Water https://www.dcwater.com/projects/potomac-river-tunnel-project 2025-11-05 www.dcwater.comApril 2021Construction begins on the CSO 025/026 Sewer Separation Project.CSO 025 / 026 Sewer Separation Project DC Water https://www.dcwater.com/projects/cso-025-026-sewer-separation-project 2025-11-05 www.dcwater.comSeptember 2022Construction is completed on the CSO 025/026 Sewer Separation Project.September 2023Northeast Boundary Tunnel is completed and begins operation.Northeast Boundary Tunnel Project DC Water https://www.dcwater.com/projects/northeast-boundary-tunnel-project-0 2025-11-05 www.dcwater.comSeptember 2024Construction begins on Canal Road NW Slope Stabilization Project.Canal Road NW Slope Stabilization Project DC Water https://www.dcwater.com/slope 2025-11-05 www.dcwater.com2024Mobilization begins on the Potomac River Tunnel at West Potomac Park.2024-2025Piney Branch Tunnel Project design and approval period.Piney Branch Tunnel DC Water https://www.dcwater.com/projects/piney-branch-tunnel 2025-11-05 www.dcwater.comFebruary 2026Canal Road NW Slope Stabilization Project estimated completion.2025-2029Piney Branch Tunnel Project estimated construction period.2030Estimate completion of Potomac River Tunnel Project.
Funding
thumb|339x339px|Vice President Joe Biden discusses the role of public and private partnerships to help leverage investments to improve the nation's infrastructure and water quality at the Anacostia River Tunnel Project in Washington, D.C. on Friday, Jan. 16, 2015.
The total capital cost of the Clean Rivers Project is estimated in the multi-billion-dollar range. The WaterNow Alliance places the overall budget at approximately $2.7 billion, including about $158 million for green infrastructure components.2019-03-01 DC Water https://tapin.waternow.org/resources/dc-water/ 2025-11-05 Tap into Resilience en-US
The DC Clean Rivers Project is financed through a combination of ratepayer charges, debt instruments (including green bonds and century bonds), inter-municipal contributions, and limited federal assistance. The program is administered by the District of Columbia Water and Sewer Authority (DC Water) to comply with a federal consent decree aimed at reducing combined sewer overflows into the Anacostia River and Potomac River.
A primary funding source is the Clean Rivers Impervious Area Charge (CRIAC), a fee assessed on property owners based on the amount of impervious surface (such as roofs and driveways) on their property. The CRIAC is the main mechanism by which DC Water recovers costs associated with its Clean Rivers obligations. The charge is described in detail by the DC Council Office of the Budget Director, which notes that it was created to fund infrastructure required by the federal consent decree.Keeping the Clean Rivers Impervious Area Charge (CRIAC) Affordable and Equitable https://www.dccouncilbudget.com/criac-1 2025-11-05 DC Council: Office of the Budget Director en-US In addition, a separate stormwater fee administered by the Department of Energy and Environment (DOEE) funds complementary green-infrastructure projects throughout the District.Stormwater Fee Background doee https://doee.dc.gov/service/stormwater-fee-background 2025-11-05 doee.dc.gov
DC Water funds much of the Clean Rivers program through long-term borrowing and bond issuance. Its Innovative Financing strategy includes instruments such as green bonds and a 100-year century bond, both designed to reduce rate impacts and attract sustainable investors.Innovative Financing DC Water https://www.dcwater.com/innovative-financing 2025-11-05 www.dcwater.com According to the WaterNow Alliance case study, DC Water issued a US $350 million green bond and a $25 million environmental impact bond to support green infrastructure under the Clean Rivers program.2019-03-01 DC Water https://tapin.waternow.org/resources/dc-water/ 2025-11-05 Tap into Resilience en-US The authority also received national recognition for its fiscal management, winning a finance award for innovation in municipal bond issuance and risk management.DC Water Wins Prestigious Finance Award DC Water https://www.dcwater.com/about-dc-water/media/news/dc-water-wins-prestigious-finance-award 2025-11-05 www.dcwater.com Because much of the project is debt-financed, a significant portion of ratepayer revenue is allocated to debt service and interest payments rather than direct construction expenditures.
Because DC Water also serves portions of suburban Maryland and Northern Virginia, neighboring jurisdictions contribute through inter-municipal agreements that allocate costs proportionally to their wastewater flows. Federal assistance has been limited but includes loans through the Water Infrastructure Finance and Innovation Act (WIFIA) and similar programs that supplement local funding.US EPA OW 2015-08-10 Water Infrastructure Finance and Innovation Act (WIFIA) https://www.epa.gov/wifia 2025-11-05 www.epa.gov en
Public Opinion
Throughout the process, DC Water has invited public input and promoted transparency by soliciting feedback through public comment periods and meetings. The transparency measures yielded positive results, with the public expressing satisfaction over the elimination of odor and improvement in water quality. Through community input, the Anacostia River Tunnel Project may open new opportunities for riverside development and improvements to green areas.Charde SustainabilityOpinionBy Seth How the Anacostia Tunnel System is transforming water quality and river access in DC https://ggwash.org/view/100485/how-the-anacostia-tunnel-system-is-transforming-water-quality-and-river-access-in-dc 2025-11-06 ggwash.org en The management of these projects has been particularly engaged with their communities, soliciting feedback during public comment periods, such as the Piney Branch Tunnel Project. DC Water engaged with the community by creating an art competition called “Art for Clean Rivers,” aiming to raise public awareness, particularly among students, about the project and build a positive association with the goals of the Clean Rivers Project.DC Water Engages Community Through Art & Creativity https://www.nacwa.org/news-publications/news-detail/2020/02/19/dc-water-engages-community-through-art-creativity 2025-11-06 www.nacwa.org
The primary source of negative public perception is the project's high cost and the method of funding, which some perceive as unjust and regressive. CRIAC has accrued controversy as critics claim the fee is regressive and disproportionately taxes low-income residents, requiring them to pay for a public works project that serves the entire city.CRIAC: How to Equitably Pay for Clean Rivers https://www.anacostiaws.org/blog/criac-how-to-equitably-pay-for-clean-rivers.html 2025-11-06 Anacostia Watershed Society en-GB Public discussion has also included the disproportionate financial burden DC residents and businesses face to provide massive environmental benefits to the entire metropolitan area compared to Maryland and Virginia residents.2012-06-01 Opinion D.C.’s big sewer dig: Why the whole region should pitch in en-US The Washington Post https://www.washingtonpost.com/opinions/dcs-big-sewer-dig-why-the-whole-region-should-pitch-in/2012/06/01/gJQAhu4l7U_story.html 2025-11-06 0190-8286 Budgeting was an internal debate on the cost-effectiveness of methods and goals. The Potomac River Tunnel was considered for budget cuts due to its $1.2 billion price tag, and shows an effort to find more affordable, alternative compliance solutions to the original 2005 consent decree.Why A Plan To Keep Sewage Out Of The Potomac Was On The Chopping Block https://wamu.org/story/20/02/20/why-a-plan-to-keep-sewage-out-of-the-potomac-was-on-the-chopping-block/ 2025-11-06 WAMU en Ultimately the plan was not changed but serves as an important step in the public works project to balance the need with the cost and the ability to adapt plans to adapting needs.
Subprojects
First Street Tunnel Project
The First Street Tunnel (FST) is the Bloomingdale/LeDroit Park flood-relief piece of Clean Rivers. That neighborhood sits at a hydraulic low point and was hit by four brutal storms in summer 2012 — photos of basements full of sewer water are what pushed the Mayor and DC Water to accelerate this part of the program ahead of the original tunnel sequence. DC Water’s page says straight out that the goal was to “mitigate sewer flooding and basement backups” in a highly urbanized neighborhood where some facilities are less than 10 ft from people’s front steps. The purpose of the project is to give the undersized combined sewers a big underground "relief tank" during storms, protect houses from backups (politically critical, not just environmental), and create a connection that can eventually send the stored water to the bigger Anacostia/NEBT system and then to Blue Plains.First Street Tunnel https://www.usa.skanska.com/what-we-deliver/projects/124134/First-Street-Tunnel 2025-11-06 www.usa.skanska.com en-US
The FST will serve as a local storage tunnel that sits right under First Street NW. During a cloudburst, flow is diverted from the old shallow combined sewer to the tunnel through drop shafts. When the storm is over and capacity returns in the main system, the captured flow is bled back and ultimately goes to Blue Plains for treatment. DC Water described it as "a large underground storage tank" in its 2016 Clean Rivers newsletter. Because it was built in a dense rowhouse neighborhood, DC Water had to stage in tiny sites, control noise, and coordinate with residents. DC Water has posted on their FST page, "success... can be attributed to a well-informed and supportive public." and is insightful on the role of social licensing to build megaprojects in cities. FST isn't an isolated tunnel but a feeder tunnel, it will connect the other Clean Rivers Project tunnels. In 2022-2023 DC Water briefly took FST out of service to do work needed to commission the bigger Northeast Boundary Tunnel and properly interconnect the tunnel systems.
Blue Plains Tunnel Project
The Blue Plains Tunnel (BPT) is the component that brings that captured CSO water right to the treatment plant and lets DC Water actually treat it. If you capture CSO but cannot empty the tunnel, the next storm will overflow again. So, BPT is the hydraulic "tail" of the whole system.Blue Plains Tunnel Project DC Water https://www.dcwater.com/projects/blue-plains-tunnel-project?utm_source=chatgpt.com 2025-11-07 www.dcwater.com The project consists of the Blue Plains Tunnel, which carries the stored CSO flow to the plant, the Tunnel Dewatering Pump Station (TDPS), very large pumps that lift tunnel water up into treatment, and an Enhanced Clarification Facility (ECF). The ECF uses fine screening, ballasted flocculation, disinfection/dechlorination; used especially when storm flow is too big to go through the full secondary process. Construction on the ECF began in August 2014 and was completed in 2018, on schedule with the consent decree.Tunnel Dewatering Pump Station and Enhanced Clarification Facility DC Water https://www.dcwater.com/projects/tunnel-dewatering-pump-station-and-enhanced-clarification-facility?utm_source=chatgpt.com 2025-11-07 www.dcwater.com
The 2017 EPA fact sheet for Blue Plains says: once the Blue Plains Tunnel and dewatering train are in service, captured tunnel water is sent to secondary treatment when capacity exists; anything above that goes through high-rate clarification, is disinfected, and is discharged as permitted Outfall 001. That's why EPA could give DC Water a 384-MGD design capacity and still expect them to meet bacteria and nutrient limits.Rock Creek Green Infrastructure Project C DC Water https://www.dcwater.com/projects/rockcreekgreenc?utm_source=chatgpt.com 2025-11-07 www.dcwater.com The Clean Rivers Project includes back end treatment plant revision and is a good example of "gray + process optimization", -- software and hardware together.
Anacostia River Tunnel Project
DC Water calls this “the second in a series of four tunnels” to control Anacostia CSOs — so it sits between the Blue Plains reach and the Northeast Boundary Tunnel (NEBT) reach. The Anacostia River Tunnel (ART) is 23 ft in diameter and about 12,500 ft long from RFK Stadium to Poplar Point. It captures the CSOs that used to discharge straight into the Anacostia, which before Clean Rivers could be 80+ events per year. The Anacostia was the first focus of the Clean Rivers Projects because it was the dirtiest and most EJ-sensitive river. DC Water's 2025 newsletter still shows that, in an average year, the Anacostia used to get ~391 million gallons of CSO, now cut drastically by the tunnel system.Fall 2025 Clean Rivers Project News: Combined Sewer Overflow (CSO) Control Activities https://www.dcwater.com/sites/default/files/document/2025-10/documents/MB25002%20CSO%20Fall%202025%20web%20version.pdf?utm_source=chatgpt.com District of Columbia Water and Sewer Authority Biannual Report
The tunnel is a deep 23 ft bored tunnel with multiple drop shafts that intercept CSO structures along the river and connects downstream to the Blue Plains Tunnel for treatment. The ART was built in heavy urban/federal context (around RFK, near National Park Service land), so the project had to coordinate with NPS. DC Water says the Anacostia tunnel system (ART + earlier Anacostia segments + later NEBT connection) will get 98% CSO reduction on the Anacostia, which is the highest of the three rivers -- better than Potomac and Rock Creek. When NEBT was turned on in September 2023, all that extra Northeast flow now goes into the same Anacostia/Blue Plains tunnel chain -- that's why you see DC Water briefly taking the First Street Tunnel offline in 2022-2023.First Street Tunnel winter construction is key step before commissioning Northeast Boundary Tunnel DC Water https://www.dcwater.com/about-dc-water/media/news/first-street-tunnel-winter-construction-key-step-commissioning-northeast?utm_source=chatgpt.com 2025-11-07 www.dcwater.com
Potomac River Tunnel Project
The Potomac River Tunnel (PRT) is the last giant piece -- 5.5 miles long, 18 ft internal diameter, under Georgetown/downtown corridor, controlling the Potomac CSOs that were still overflowing ~77 times a year and dumping ~677 million gallons in an average year as of the 2025 newsletter. DC Water's board approved the $819 million design-build contract on October 6, 2023 -- their largest contract ever.DC Water Awards $819 Millon Contract for Potomac River Tunnel DC Water https://www.dcwater.com/about-dc-water/media/news/dc-water-awards-819-millon-contract-potomac-river-tunnel?utm_source=chatgpt.com 2025-11-07 www.dcwater.com The Potomac overflows are very visible (riverfront is a recreation/tourist area). It is the most expensive single package, so it's the one that pushes CRIAC up again just when people thought bills might stabilize. It runs under/near federal land and Rock Creek Park, so there are access closures, night lane restrictions, and slope-stabilization works -- DC Water warned the public about that in 2024-2025 notices.Spring 2024 Potomac River Tunnel construction has begun!, Clean River Project News https://www.dcwater.com/sites/default/files/document/2024-03/documents/CSO_Spring_2024_2.pdf?utm_source=chatgpt.com Combined Sewer Overflow (CSO) Control Activities, District of Columbia Water and Sewer Authority Biannual Report
When finished (DC Water maintains that completion will be "by 2030"), PRT will bring the Potomac reduction to ~93% and close out the 2005 consent decree tunnel requirements. It will connect back to the Blue Plains exactly like the other tunnels. PRT faces unique challenges such as deep shafting in mixed geology close to the river, staging in insanely tight, high-value real estate, multiple outside reviewers (NPS, NCPC, DDOT), and community disruptions such as single-lane traffic at night, trail closures, and noise.DC Water Celebrates Completion of the Northeast Boundary Tunnel DC Water https://www.dcwater.com/about-dc-water/media/news/dc-water-celebrates-completion-northeast-boundary-tunnel?utm_source=chatgpt.com 2025-11-07 www.dcwater.com
Piney Branch Tunnel Project
Piney Branch is the newest and final tunnel component and is the Rock Creek piece of the Clean Rivers Project. DC Water says about 40 million gallons/year of combined sewage currently spill from CSO 049 into Piney Branch (a tributary of Rock Creek) in an average year, about 25 times a year. The Piney Branch Tunnel will capture at least 4.2 million gallons per event and cut those overflows by 96%, down to one overflow per year. That's the same performance target as the bigger tunnels, just scaled to a smaller creek. This project is located inside Rock Creek Park, which is a historic district and federal parkland, so DC Water had to go to NCPC, NPS, and the Commission of Fine Arts. NCPC's January 2025 staff report approved preliminary plans but noted the project will clear ~2 acres of forest and must restore the site after construction. That makes this project more "environmental-process heavy" than the earlier tunnels.January 9, 2025 Piney Branch Tunnel Project Executive Director's Recommendation https://www.ncpc.gov/docs/actions/2025January/8434_Piney_Branch_Tunnel_Project_Staff_Report_Jan2025.pdf?utm_source=chatgpt.com National Capital Planning Commission
The Piney Branch Tunnel Project aims to build a diversion at CSO 049, send the flow into the new storage tunnel, and hold it there until the East Rock Creek Diversion Sewer has capacity, then let it flow by gravity to Blue Plains.Piney Branch Tunnel: The Problem - Combined Sewer Overflows https://www.dcwater.com/sites/default/files/project/2022-07/documents/DC%20WATER%20PINEY%20BRANCH%20TUNNEL%20-%20MT%20PLEASANT%20LIBRARY%20PUBLIC%20MEETING%20-16-25.pdf?utm_source=chatgpt.com DC Water Originally the 2016 decree amendment said DC could control Rock Creek with green infrastructure on 365 acres and skip the Rock Creek Tunnel. Green Infrastructure worked, but not everywhere -- so DC Water is now building Piney Branch as a targeted, smaller tunnel to mop up one of the worst Rock Creek outfalls. Schnabel Engineering even calls it "the final tunnel project for the DC Water Clean Rivers Program."DC Waters Clean Rivers Program https://www.schnabel-eng.com/projects/dc-water-clean-rivers-project/ 2025-11-07 Schnabel Engineering en-US Public meeting material in 2025 show a required "place in operation" date of November 23, 2029 -- still inside the overall "done by 2030" frame. Clean Rivers did not end with the Northeast Boundary Tunnel but is continuously adding components.
Green Infrastructure
Green infrastructure is one of the approaches in the Clean Rivers Project to meet the 2005 consent decree, offering lower investment and impact. The new infrastructure aims to harness natural processes, such as evapotranspiration and infiltration, to slow down, clean, and potentially reuse stormwater, thereby preventing it from overflowing into sewer systems and contaminating waterways. The approach takes from natural environmental processes through the use of plants, trees, and mimicking ground permeability.Green Infrastructure DC Water https://www.dcwater.com/resources/environment/cleanrivers/projects/green-infrastructure 2025-11-06 www.dcwater.com The green infrastructure projects include rooftop collection practices, permeable pavements, and bioretention efforts (increasing vegetation and permeable soil). These projects were included in many of the other DC Clean River Projects, such as the Potomac River and Rock Creek projects. These efforts began to see benefits as early as 2017, including increased property values, beautified neighborhoods, reduced extreme summer temperatures, preservation of natural habitats, enhanced public spaces, and creation of local green jobs.